ELECTRICAL PROJECTS

IPS in action

SELECTED WORK

BUILT TO KEEP
OPERATIONS
MOVING.

Each project embodies the same philosophy, of understanding the field conditions, co-ordinating the requirements and delivering the systems fit for purpose

Deer Valley Water Treatment Plant

25 new variable frequency drives installed around a running plant, with more than 125,000 feet of power and control conductor pulled.

4AB-10 24th St Water Treatment Plant (Zone 3D and 4A)

Electrical BPS/PRV station for the first section of the Zone 4A improvements, including 5kV gear, instruments and conductors.

Union Hills Water Treatment Plant

Plant-wide modernization: 5kV and 480V switchgear and MCCs, blower upgrades, a chlorine scrubber and four PLC replacements.

Shearer’s Phoenix Twin Screw Line

A new twin-screw production line powered from a 4,000A utility service through to startup and commissioning.

91ST Ave Fire Rehab Water Treatment Plant

A fire took out an electrical room. IPS rerouted power, secured replacement gear and had the plant running again in four days.